Tasks

Work in a project with an owner and a duration, scheduled on the critical path.

A task is work in a project that takes time, such as "Sign the lease". You give it an owner and a duration, and Continual schedules it.

How it works

You give each task:

  • An Owner, a person or Continual.
  • A Kind: Work takes its owner's time; a Wait is time that must pass while nobody works, such as a permit review; a Milestone takes no time and marks a date others rely on.
  • A Duration in working days, Monday to Friday. A milestone's duration is 0.
  • Optionally, a Start no earlier than date and a Due date.

A task moves from Backlog or Planned to In progress and Done, or is Canceled. You decide when it is done, using its completion criteria, comments, and attachments. Each task gets a number, such as TASK-21. Move to moves a task to another project and keeps its number and dependencies.

A task is planned work, not a to-do: it does not appear in anyone's Up next. When a task needs a person, a to-do about it asks them.

Follow the schedule

You never enter a task's scheduled dates. Continual computes them from its duration, what it waits for, and its fixed dates, and the task's Schedule section shows them:

  • Scheduled start, Scheduled finish, Late start, Late finish, and Slack. A task with no slack is Critical.
  • Actual start and Actual finish, from the day it went in progress and the day it was done.

Backlog and canceled tasks are not scheduled. If dependencies form a loop, the tasks in it get no dates. A dependency on a task in another project blocks the task but does not move its dates yet.

The tasks list has views for this: Critical path lists the unfinished tasks with no slack, Schedule is a timeline of scheduled dates, and Board groups tasks by status.

Ready and Blocked

Continual also marks each unfinished task:

  • Ready when it has an owner and completion criteria.
  • Blocked while a task it waits for has not finished, or, for a start-to-start dependency, not started.

Object: changes freely, and its history keeps the old values.

Status

  1. Backlog
  2. Planned
  3. In progress
  4. Done
  5. Canceled

Fields

Project
Link to a project
NumberSet by Continual
Number, such as TASK-12
Title
Text
Description

Context, instructions, and the intended outcome.

Formatted text
Completion criteria

The observable result and evidence needed to accept this work.

Formatted text
Priority
Low, Normal, High, Urgent
Kind

Work takes its owner's time; a wait is time that must pass while nobody works, such as a permit review or a delivery's lead time; a milestone takes no time and marks a date others rely on.

Work, Wait, Milestone
Duration

Working days it takes, Monday to Friday. A milestone takes none.

Number
Start no earlier than

A fixed day it cannot start before, such as when a delivery arrives. Leave it empty when what it waits for decides.

Date
Due date

The day it must finish by. A task scheduled to finish later has negative slack.

Date
Attachments
List of group of values
Owner

Who answers for it and reports its progress.

Link to a member or service account
Related to
Links to records
Scheduled startSet by Continual

The earliest day it can start, from what it waits for. For a task already started, the day it started.

Date
Scheduled finishSet by Continual

The day it is scheduled to finish, from its start and duration.

Date
Late startSet by Continual

The last day it can start without moving the project's finish or a due date.

Date
Late finishSet by Continual

The last day it can finish without moving the project's finish or a due date.

Date
SlackSet by Continual

Working days it can slip before it moves the project's finish or a due date. Negative when it is already late.

Number
CriticalSet by Continual

On the critical path: it has no slack, so any slip moves the finish.

Yes or no
Actual startSet by Continual

The day it went in progress, from its history.

Date
Actual finishSet by Continual

The day it was done, from its history.

Date
MarksSet by Continual

Continual keeps these current, each with the reason it holds.

Ready, Blocked

Actions

  • Move to. Moves the task, with its comments and to-dos, to another project. Whoever reaches that project reaches it; its number stays.