Dependencies

What a task waits for: another task's finish or start, with a lag in working days.

A dependency says what a task waits for, such as "Furnish the office" waiting for "Sign the lease" to finish. Continual schedules tasks from their dependencies.

How it works

You add a dependency on the task that waits, under Waits for. Choose the task it waits for and the Type:

  • Finish to start: it starts once the other task finishes. This is the default.
  • Start to start: it starts once the other task starts.
  • Finish to finish: it finishes once the other task finishes.

Add a Lag in working days if the task must wait longer, such as two days for paint to dry. A task cannot wait for itself, and it waits for another task at most once.

Deleting either task deletes the dependency. If dependencies form a loop, Continual leaves the tasks in it without dates and the project says which tasks wait for each other.

Object: changes freely, and its history keeps the old values.

Fields

Task
Link to a task
Waits for

The task whose finish or start it waits for.

Link to a task
Type
Finish to start, Start to start, Finish to finish
Lag

Working days between the other task's finish or start and this one's.

Number